Skip to content
Agentmart
Submit a tool

project-sizing-guide

Software project effort estimation assistant.

Skill by zebbern

IndexedMIT★ 4,678
Write a review

Install

Works with Claude Code, Claude apps, Codex, Cursor, Gemini CLI, GitHub Copilot, VS Code, OpenCode, Goose, Windsurf. Read the repository before you give any tool access to your data.

npx agentmarket install skill/zebbern-project-sizing-guide

Asks which of your tools to add it to (Claude Code, Codex, Cursor, VS Code, Windsurf, Gemini CLI, Claude Desktop) and shows the change first. See https://agentmart.dev/cli.

Get the weekly diff

The weekly diff: one email a week with new agent tools, notable updates and grade changes, plus security alerts for tools you follow. Double opt-in, one-click unsubscribe.

We use your email only for this newsletter. Privacy

About

Software project effort estimation assistant. Outputs three-point estimates (optimistic/most-likely/pessimistic values with confidence intervals), T-shirt sizes, or Function Point Analysis (FPA) counts. Triggered when users ask 'how long will this feature take,' need to assess project workload, perform PERT estimation, T-shirt sizing, FPA, sprint planning, or quote-based effort breakdowns.

No reviews yet. Installed it? Reviews come from verified installers only. How reviews work

Permissions

What this skill can do and what it asks for, from its SKILL.md and code. Checked Oct 25, 2026.

Tools
No tools found
Secrets
None asked for
Install scripts
None found
Runs as
Python package

Network hosts it talks to 1

  • codeload.github.com · found in install command

Files it touches

  • ~/.claude/skills/project-sizing-guide

What's inside

Skill name
project-sizing-guide
Description
Software project effort estimation assistant. Outputs three-point estimates (optimistic/most-likely/pessimistic values with confidence intervals), T-shirt sizes, or Function Point Analysis (FPA) counts. Triggered when users ask 'how long will this feature take,' need to assess project workload, perform PERT estimation, T-shirt sizing, FPA, sprint planning, or quote-based effort breakdowns.
License
MIT
Instructions
286 lines in SKILL.md · view on GitHub

Before installing

  • Ships executable scripts

Files (3)

  • LICENSE
  • SKILL.md
  • estimate_calculator.py · scripts/

SKILL.md (first lines)

# Project Sizing Guide — Software Project Effort Estimation

Helps teams produce scientifically grounded effort estimates for software projects, based on three major methodologies: Three-Point Estimation (PERT), T-shirt Sizing, and Function Point Analysis (FPA). Outputs optimistic, most-likely, and pessimistic values along with risk intervals.

## Quick Start

1. **User provides a requirements description** → Agent identifies functional modules and breaks them into a Work Breakdown Structure (WBS)
2. **Select an estimation method** → Choose the best-fit approach based on project stage and available information
3. **Estimate each item** → Assign O/M/P (Optimistic / Most Likely / Pessimistic) values to every work package
4. **Aggregate and report** → Generate an estimation report with risk analysis and confidence intervals

A calculation helper is available:
```bash
python3 scripts/estimate_calculator.py --method pert --tasks '[{"name":"User Login","O":2,"M":3,"P":8}]'
```

---

## Method Selection Guide

| Scenario | Recommended Method | Rationale |
|----------|-------------------|-----------|
| Early feasibility study, rough budgeting | T-shirt Sizing | Little information available; quickly align on order of magnitude |
| Sprint planning, iteration estimation | Three-Point Estimation (PERT) | Good granularity with confidence intervals |
| Contract bidding, large-project RFPs | Function Point Analysis (FPA) | Most rigorous; industry-comparable |
| Team has historical data | PERT + historical calibration | Combines empirical correction with data |

---

## Method 1: Three-Point Estimation (PERT)

### Core Formulas

| Metric | Formula | Meaning |
|--------|---------|---------|
| Expected Value E | (O + 4M + P) / 6 | Weighted average effort |
| Standard Deviation σ | (P − O) / 6 | Estimation uncertainty |
| Variance V | σ² | Used to aggregate across tasks |
| Project Total Expected | ΣE | Sum of individual expected values |
| Project Total Std Dev | √(ΣV) | Square root of summed variances |

Where:
- **O** (Optimistic): Shortest duration assuming everything goes smoothly
- **M** (Most Likely): Duration under normal circumstances
- **P** (Pessimistic): Longest duration when significant difficulties arise

### Confidence Intervals

| Confidence Level | Interval | Use Case |
|-----------------|----------|----------|
| 68.3% | E ± 1σ | Internal rough estimates |
| 90% | E ± 1.645σ | Project planning |
| 95% | E ± 2σ | External quotes |
| 99.7% | E ± 3σ | Contractual commitments |

### Steps

1. **Build the WBS**: Decompose requirements into the smallest independently estimable units (recommended ≤ 5 person-days each)
2. **Three-point estimation**: For each work package, provide O / M / P values (use consistent units: person-hours or person-days)
3. **Calculate per-task expected value and standard deviation**
4. **Aggregate project-level metrics**: Total Expected = ΣE, Total Std Dev = √(Σσ²)
5. **Output confidence intervals**: Choose a confidence level based on risk appetite

### O/M/P Estimation Rules of Thumb

- O should not be less than 30% of M (overly optimistic suggests essential steps were overlooked)
- P should not exceed 5× M (overly pessimistic suggests unclear requirements that need clarification first)
- If O ≈ M ≈ P, the task is either extremely well-understood or the estimator hasn't seriously considered risks
- The P/O ratio (spread ratio) reflects uncertainty: < 2 = low risk, 2–4 = medium risk, > 4 = high risk

---

## Method 2: T-shirt Sizing

### Size Reference Table

| Size | Typical Range (person-days) | Typical Story Points | Suitable For |
|------|----------------------------|---------------------|--------------|
| XS | 0.25 – 0.5 | 1 | Config changes, copy edits, simple bug fixes |
| S | 0.5 – 2 | 2 – 3 | Single-component development, simple API, minor UI tweaks |
| M | 2 – 5 | 5 – 8 | Complete feature module, moderately complex API |
| L | 5 – 15 | 13 – 21 | Cross-module features requiring integration |
| XL | 15 – 40 | 34 – 55 | Subsystem-level development requiring architecture design |
| XXL | 40+ | 89+ | Should be split across multiple iterations; not recommended as a single estimation unit |

### Converting T-shirt Sizes to Three-Point Estimates

When more precise numbers are needed, T-shirt sizes can be converted to three-point estimates:

| Size | O (person-days) | M (person-days) | P (person-days) |
|------|-----------------|-----------------|-----------------|
| XS | 0.25 | 0.5 | 1 |
| S | 0.5 | 1 | 2.5 |
| M | 2 | 3.5 | 7 |
| L | 5 | 10 | 20 |
| XL | 15 | 25 | 50 |
| XXL | 40 | 70 | 150 |

### Steps

1. **Team alignment**: Confirm what each size means (the table above is a reference; teams may customize)
2. **Independent assessment**: Each person assigns a size independently to avoid anchoring bias
3. **Discuss discrepancies**: When estimates differ by more than 2 sizes, a discussion is mandatory
4. **Reach consensus**: Adopt the team consensus value
5. **Convert to numbers** (optional): Use the table above to derive O/M/P values

---

## Method 3: Function Point Analysis (FPA)

### Five Function Component Types

| Component Type | Abbreviation | Definition | Example |
|---------------|-------------|-----------|---------|
| Internal Logical File | ILF | Logical data group maintained by the application | Users table, Orders table |
| External Interface File | EIF | Data group referenced but not maintained by the application | Third-party exchange rate data |
| External Input | EI | Data processing entering the system from outside | Form submission, API POST |
| External Output | EO | Data generated and sent outside the system | Report generation, exports |
| External Inquiry | EQ | Simple data retrieval + display | List queries, detail pages |

From zebbern/claude-code-guide, MIT.

More from zebbern/claude-code-guide

Signals

Stars
4,678
Forks
471
Open issues
3
Last commit (this folder)
May 31, 2026 (4 months ago)

From GitHub (fetched Oct 24, 2026).

Details

License
MIT
First seen
Oct 24, 2026
Last checked
Oct 24, 2026

More from zebbern

Cite this page

project-sizing-guide skill. Agent Mart. https://agentmart.dev/skills/zebbern-project-sizing-guide (last updated 2026-10-24)